Costing and the Quantity Surveyor
An architect designs the house. A quantity surveyor (QS) tells you what it will actually cost to build, and checks that what you are billed matches what was built.
1. Do You Need a QS?
For a modest single-storey house, many people rely on their architect's estimate and comparable contractor quotations. For anything larger, or if you are borrowing significantly, a QS pays for themselves.
A QS will:
- Produce a cost estimate early, so the design can be adjusted before it is too late
- Prepare a Bill of Quantities (BOQ) — an itemised measure of every element of work
- Evaluate tenders — spot the abnormally low bid and the missing item
- Value work in progress for each payment stage
- Price variations so you are not at the contractor's mercy on extras
- Prepare the final account
2. The Bill of Quantities Is Your Main Cost Control
A BOQ lists each item of work with its measured quantity and a rate: cubic metres of concrete, square metres of blockwork, kilograms of steel, square metres of plaster.
Why it matters:
- Every contractor prices the same quantities, so quotations become genuinely comparable — see Choosing a Contractor.
- Variations get priced at agreed rates already in the BOQ, instead of whatever the contractor asks once you are committed.
- Progress payments can be measured rather than argued about.
Without a BOQ, you are negotiating every extra from a position of no information.
3. Cost Estimation
Construction cost in Mauritius is commonly discussed as a rate per square foot of built area, varying widely with the level of finish — structure only, standard finish, or high-end.
⚠️ VERIFY — Current Rs/ft² benchmarks are deliberately not stated here, and I was unable to find an authoritative published source for them. There is no official Mauritian body publishing residential construction rates per square foot; the figures circulating online are anecdotal and age quickly. Material prices also move with import costs and the exchange rate, so a stale figure here would mislead someone's entire budget. Get current rates from:
- Two or three quantity surveyors or architects, for your specific finish level
- Recent itemised quotations from contractors on your own plans
- People who have completed a comparable house in the last 12 months
When someone quotes you a rate per square foot, always ask: what does it include? A rate that excludes finishes, boundary wall, and utilities is not comparable to one that includes them.
4. Where Budgets Break
- Finishes. Tiles, sanitary ware, kitchen, doors, and windows have an enormous price range and are chosen late, when enthusiasm is high and discipline is low. Set a finishes budget early and hold it.
- Variations. Small changes during the build, each individually reasonable. See Choosing a Contractor on written variation orders.
- Forgotten externals. Boundary wall, gate, driveway, water tank and pump, landscaping. See Financing Your House.
- Over-specified structure. As noted in Architect, unnecessarily high-end structural materials inflate cost without improving the house.
- Material price movement on a long build.
5. Buying Materials Yourself
Some owners supply some materials directly to save on the contractor's margin. Weigh it honestly:
Can work well for: tiles, sanitary ware, doors, windows, paint, light fittings — items you choose anyway and that are easy to count.
Rarely worth it for: concrete, steel, blocks, cement — contractors buy these at trade prices you will not match, and if you supply them, any shortage, wastage, or delay becomes your problem and your excuse-in-waiting for the contractor.
If you do supply materials, make the split explicit item by item in the contract, and agree who bears wastage.